By CASSIE MCKEE, Four Points News
Construction on Water Treatment Plant 4 in Four Points is more than 85 percent complete and on schedule to be finished by this summer, according to Bill Stauber, supervising engineer with Austin Water.
“We’re transitioning into the startup of equipment and startup of systems and making sure everything’s working,” Stauber said. “We’re moving into the testing and startup phase.”
Once construction is complete around July, engineers will begin testing all the plant’s equipment and systems, which means it may be sometime before the plant is fully operational.
“The plant has a lot of moving parts,” said Jason Hill, senior public information officer with Austin Water. “It’s not like you just turn the lights on. It can take a little bit of time after that to be fully operational.”